Hyper Saline Water to Boiler Feed Water Treatment Plant

Owner Petroleum Development Oman (PDO)
Estimated Value US$ 150,000,000
Sector Water
Sub Sector Water Treatment Plant
Country Oman
City Qarn Alam
Capacity 25,000 cu m. per day Feasibility Start Date Q2-2017
Status EPC ITB Project End Date Q3-2022
Owner Petroleum Development Oman (PDO)
Estimated Value US$ 150,000,000
Sector Water
Sub Sector Water Treatment Plant
City Qarn Alam
Country Oman
Capacity 25,000 cu m. per day
Feasibility Start Date Q2-2017
Status EPC ITB
Project End Date Q3-2022


Project Overview


Background

Petroleum Development Oman (PDO) is developing a water treatment plant that will produce steam for its thermal-based enhanced oil recovery (EOR) as well as for the treatment of hyper saline water to boiler feed. It will be located in Qarn Alam in northern Oman.


Scope of Work

The water treatment plant will save aquifer water for future purposes as well as minimize deep water disposal and safeguarding a regular and reliable supply of steam to support oil production. Treatment of hyper saline water to specifications usable by PDO will provide a sustainable solution to aquifer abstraction. PDO is expected to increase the capacity of the treatment plant of 25,000 cu m. per day of produced water to the treatment of up to 60,000 cu m. per day of produced water.

The scope of work also includes the construction of:

  • 25,000 cu m. water treatment plant
  • Inlet and outlet facilities
  • Interconnecting pipes
  • Transfer pumps and valves 
  • Water storage tanks
  • Water quality verification units


Finance

Petroleum Development Oman (PDO) is financing the construction of this water treatment plant.


Related Companies




Related Contacts


Petroleum Development Oman (PDO)

Name: Raoul M. Restucci
Designation: Managing Director
Telephone:+968 2467 7210
Email Address: [email protected]
Name: Dana Al Sarhani
Designation: Media Relations & Social Media Strategist
Telephone:+968 2467 8258, +968 9365 8711
Email Address: [email protected]
Name: Ali Gheithy
Designation: Petroleum Engineering Director
Telephone:+968 24672569
Email Address: [email protected]
Name: Abdulrahman Al Mahmood
Designation: Senior Contracts Engineer
Telephone:+968 2467 3753
Name: Abla Riyami
Designation: Project Director
Telephone:+968 2467 7442
Name: Debashish Mukhopadhay
Designation: Contracts Incharge
Telephone:+968 2467 5161
Name: Saud Harthi
Designation: Contract Engineer
Telephone:+968 2467 7676


Updates

Sep 2017

PDO has issued tenders inviting companies to submit their bids for being the technology provider and for the EPC contract. Bid submission deadline is on 7th November.

Aug 2017

Construction of the plant will be carried out on a design, build, own, operate and transfer (DBOOT) basis.

May 2017

Petroleum Development Oman (PDO) is carrying out the feasibility study for developing a water treatment plant that will produce steam for its thermal-based enhanced oil recovery (EOR) as well as carry out the treatment of hyper saline water to boiler feed.